On 3 February 2017, the Court of Appeal released its decision in the case of CJ Parker Construction Ltd (in liq) v Ketan [2017] NZCA 3. Observing that the consequences for not complying with the scheme under section 23 of the Construction Contracts Act 2002 may be draconian, Justice Toogood observed that “a pragmatic, common sense and contextual approach” was required when considering the validity of a payment claim in terms of section 20. More critically, the Court of Appeal has perhaps thrown a lifeline to owners who are unable to provide a valid payment schedule for an amount less than claimed, if the payment claim itself provid